Predictability, stability seen as essential for Romania’s new solar boom

Nov 16
5 min read

Nov 10, 2026, Article by Veselina Petrova


Romania’s solar market has entered a new phase of growth, driven by strong market fundamentals, favourable policies and EU decarbonisation targets, but key challenges still need to be addressed to sustain the expansion and ensure a stable environment, industry experts said at the first InterSolar Eastern European Solar, Storage and Flexibility Summit held in Romania.

Romania’s solar photovoltaic (PV) market has come on the radar after the country commissioned 2.2 GW of new solar parks in 2025 and brought its cumulative installed solar capacity to over 7 GW, according to statistics by the Romanian Photovoltaic Industry Association (RPIA).

The strong fundamentals have already started the boom and the country claims to be one of the markets where the installation pace is the fastest. Nevertheless, hurdles such as grid connection capacity, regulatory predictability and financing guarantees are still on the way, with grid access being the critical bottleneck. And what is most needed to back the rollout is to achieve stability and predictability without changing the rules during the game, said David Wedepohl, managing director international affairs at German Solar Association BSW, referring to Germany’s experience.

According to Mihaela Nyerges, managing partner at Nyerges and Partners, the next challenge will be to convert the development pipeline into financeable, grid-connected projects without allowing connection rules and financial requirements to become obstacles.


STRONG FUNDAMENTALS

The solar market in Romania is underpinned by a combination of strong natural resources, land availability, an urgent need for new generation capacity and an improving regulatory framework. The country benefits from good solar irradiation and extensive areas of flat, less agriculturally productive land suitable for PV deployment. After nearly a decade of limited investment in new generation capacity, the planned phase-out of coal-fired power plants and the need to meet EU climate targets have further strengthened demand for new projects.

Regulatory changes have played a crucial role, particularly reforms introduced in 2022–2023 that removed the requirement to amend urban planning documentation for eligible renewable energy projects before starting the construction permitting process. This major change has helped cut permitting timelines by around a year and significantly raised the installation pace, making the market more attractive to investors.

Apart from permitting simplification, the CfD scheme was introduced in 2024 to serve as an alternative to directly negotiated long-term PPAs, which were banned in 2012 after driving state-owned hydropower plant operator Hidroelectrica into insolvency. The law restricted directly negotiated physical bilateral electricity contracts, including PPAs, and required wholesale transactions to be conducted through centralised trading mechanisms such as OPCOM. The ban was lifted in steps starting in May 2020, followed by a full and definitive removal that came into effect at the end of 2021. The CfD mechanism, meanwhile, came to provide certainty and make projects more bankable. “It's a very good scheme. So banks are really interested in financing projects that secured CfD,” Mihaela Nyerges commented.

The first round of CfD tenders was completed in 2024 and awarded contracts to 432 MW of solar projects, followed by a second round a year later that distributed 1,488 MW of solar.

Additionally, grants are being allocated for solar PV projects under various programmes, including the National Recovery and Resilience Plan (PNRR) and through the Modernisation Fund. Data released by the Ministry of Energy and the Ministry of Investments and European Projects (MIPE) shows that Romania’s PNRR had a total allocation of EUR 1.62 billion, of which EUR 610 million was earmarked for onshore wind and solar. Under the EU’s Modernisation Fund, Romania rolled out an allocation mechanism for renewable power generation and storage capacity, allocating EUR 815 million to incentivise investments in green energy and enhance grid stability.


GRID CONGESTION

Romania has for a long time had a grid connection system functioning under the first-come, first-served model, under which developers only needed low upfront costs and financial guarantees to secure grid connection rights. As solar developments grew exponentially, the physical transmission network could not keep up, resulting in “paper congestion” with speculative projects with secured rights to connect to the grid that might not be built. According to data from the Romanian Energy Regulatory Authority (ANRE), around 115 GW of projects held grid connection rights as of September 1, far exceeding the realistic development prospects.

To eliminate speculative projects that reserve grid capacity but don’t “see the sunlight,” ANRE introduced successive measures in May to prevent new projects from entering the system and to clear up the grid of projects that are not advancing at the required pace. The measures include introducing auctions for allocating available connection capacity for new production and storage projects, lifting financial guarantees for grid connections to 20% of connection tariffs from 5% before and imposing auction participation and building permit financial guarantees.

Additionally, stricter development deadlines were introduced that require projects to secure permits within 12 months of signing connection agreements and within 18 months from the issuance of the technical grid connection permit, or ATR. Failure to meet those deadlines would result in the loss of grid connection rights.

“This overview of what's happening in the Romanian market is not necessarily something uncommon, let's say, in the wider European context. And we see the shift away from the first-come, first-served to a different system. In the end, I think this approach is going to create stability long-term,” Wedepohl said.


NEED FOR REFINEMENT

The shift away from the “first come, first served” model to the new capacity allocation mechanism is already in progress, with bidding in the first auction being scheduled for October 30. The framework applies to new solar, wind, storage and combined power projects with an installed capacity of 5 MW or more. The window closed with 12 applications covering 491 MW and TSO Transelectrica is conducting an extensive study for the available network capacity to identify the exact grid reinforcement and network upgrade works needed to accommodate the requested capacity. After placing an auction participation guarantee, developers will bid for specific capacities allocated year-by-year across a 10-year allocation period.

“The introduction of an early-stage financial guarantee of EUR 20,000 (USD 22,440) per MW, despite limited visibility on key auction parameters, has made 2026 an experimental year,” Mihaela Nyerges said. The guarantee that developers need to provide in order to express their interest will secure the subsequent bid placement, though there is no visibility on what capacity will be allocated and when, which explains the low interest in the tender, she commented.

Another notable regulatory change adopted in 2026 is the introduction of a financial guarantee of EUR 30 per kW of installed capacity when applying for a setting-up/establishment authorisation, representing a strong financial deterrent against abandoning or dragging out projects. Meanwhile, strict deadlines were also announced for securing construction authorisation, requiring developers to obtain building permits within 12 months of signing a connection contract and within 18 months of receiving an ATR.

In all, the new capacity allocation mechanism was described as “significant” and “dramatic” and, while necessary, its implementation was considered insufficiently predictable for investors. The guarantee associated with the establishment authorisation, according to Mihaela Nyerges, is a positive measure that will filter out speculative projects, though its calculation based on cumulative installed capacity, rather than approved export capacity, could potentially increase costs for hybrid projects combining solar, wind and storage.


 
 
 